How air conditioning is installed: survey to switch-on

By Alex Christou. 2 sources listed at the end.

On this page
Get a rough quote from your phoneThree questions, three priced options. Free.

Quick answer. A single-room split system is usually fitted, tested and handed over in one day; installers we list put it at 4 to 8 hours per unit. Multi-room and ducted systems take one to four days. Before that comes a survey, often free: 436 of the 1,769 installer listings we hold say so on their own website.

The installer statements below come from our records, each checked against the firm's own website between October and November 2026.

The process at a glance

Stage What happens
1. Enquiry You describe the rooms; some firms give an instant estimate
2. Survey Room sizing, outdoor unit position, pipe and cable route
3. Quote Written price with model, kW rating and what is included
4. Install day Units fixed, pipes run, wiring, drain. Single split: usually one day
5. Commissioning Pressure test, vacuum, refrigerant charge, performance check, on install day
6. Handover Controls walk-through, warranty registered

Install timings below are typical figures from installer websites, not guarantees. Your survey should give you a firm timescale for your home.

Step 1 and 2: the survey

Most installers price after a visit because the job depends on your walls, not just your rooms. Airconcool in London says its free survey confirms the right unit size, system type, outdoor unit location and installation route. Be Cool Group says it books routine install surveys within 48 hours.

Free surveys are common in the South East. Kent has 36 installers on our free survey list for Kent, and Hampshire has 34 on its free survey page. Some firms charge and credit the fee back if you go ahead, so ask before anyone visits.

Before the survey, run the size calculator so you know roughly what kW rating to expect. If a quote comes back far bigger or smaller, ask why.

Step 3: the quote

A good quote names the make, model and kW rating, says where the outdoor unit goes, how much pipe run is included, who does the electrical work and whether VAT is included. Our guide to comparing air conditioning quotes has the full checklist, and the air conditioning cost guide explains what moves the price.

Check the firm's F-gas company certificate. gov.uk says a company must be certified to install equipment containing F gas, and that covers every split system.

Step 4: install day

For a standard split system, the day usually runs like this:

  1. Indoor unit. A mounting plate goes on the wall and a core hole is drilled through to the outside for the pipes, cable and condensate drain.
  2. Outdoor unit. Fixed on a ground stand, wall bracket or flat roof. Higher brackets need ladders or access equipment, which can add time.
  3. Pipework and cable. Two insulated copper pipes and a control cable link the units, often hidden in trunking. Longer runs take longer.
  4. Drain. The condensate runs out by gravity, or through a small pump where that is not possible.
  5. Power. The system may need its own circuit from the consumer unit; the quote should say who does that work.

How long installers say it takes:

Installer What they say
Infinity Energy Services, Southampton A single split is typically fitted, commissioned and tested in a day; multi-splits usually take longer
Polarcool Refrigeration, Maldon Single-room split typically one day; multi-split one to two days
Airvana, London Single-room installs one day; multi-room or concealed ducted two to four days
Airconcool, London Most standard residential installs 4 to 8 hours per unit
CAL Electrical Solutions, Huntingdon Single-room wall-mounted system usually fitted and commissioned in a day
Lenham Air, Kent Typically installed within a day per room

The pattern is clear: one room, one day. Each extra indoor unit, a ducted system or a difficult outdoor position adds time. If you are weighing several rooms, our multi-split guide covers the trade-offs.

Step 5: commissioning

This is the part you can't see, and the part that decides how long the system lasts. Be Cool Group lists its commissioning as a pressure test, vacuum, refrigerant charge, performance check and electrical safety test. The pressure test proves the pipe joints hold; the vacuum pulls air and moisture out of the pipes before the refrigerant goes in.

Ask your installer to confirm these steps were done. It is a fair question and a good firm will answer it without fuss.

Step 6: handover and paperwork

You should get a walk-through of the remote or app, the warranty registered with the manufacturer, and any paperwork for the electrical work. gov.uk lists putting in a fixed air-conditioning system among the jobs that might need building regulations approval; if your installer is registered with a competent person scheme, you do not need to apply yourself. Ask how they handle it before work starts.

Many longer warranties need a yearly service to stay valid. Our servicing guide explains what that visit covers.

Planning permission

Whether you need planning permission depends on the type of unit, the building and where the outdoor unit goes, and flats, listed buildings and conservation areas have tighter rules. Read our guides on planning permission in Brighton and Hove and planning permission in London before the survey, so the outdoor unit position on the quote is one you can use.

Questions

Can air conditioning be installed in one day?
A single-room split usually can. Installers we list in Hampshire, Essex, Cambridgeshire, Kent and London all say a standard single split is fitted and commissioned in a day, and one London firm puts it at 4 to 8 hours per unit.
How long does a multi-room air conditioning install take?
Longer. An Essex installer says one to two days for a multi-split and a London firm says two to four days for multi-room or concealed ducted systems. The survey should give you a timescale for your home.
What happens at an air conditioning survey?
The installer checks the rooms, sizes the unit, picks the outdoor unit position and works out the pipe and cable route, then sends a quote. 436 of the 1,769 installer listings we hold say on their own site that the survey is free.
Do I need building regulations approval for air conditioning?
gov.uk lists putting in a fixed air-conditioning system among the jobs that might need approval. You do not need to apply yourself if the work is done by someone registered with a competent person scheme, so ask your installer how they handle it.
Is it messy to have air conditioning fitted?
There is usually one core hole through the outside wall for the pipes, cable and drain, plus some drilling for brackets. A good installer sheets the room, tidies the pipework into trunking and cleans up before leaving.

Sources

  1. gov.uk, Building regulations approval: when you need approval and competent person schemes, read 28 Nov 2026
  2. gov.uk, Company certification to work with F gas, read 28 Nov 2026

Written and checked by Alex Christou. Found a mistake? Tell us; our corrections policy explains what happens next.